INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Problematic manufacturing slab/mat movements

Problematic manufacturing slab/mat movements

Problematic manufacturing slab/mat movements

(OP)
To give some background, an assembly table, which is prone to the slightest movement, was placed on an existing 6 inch slab-on-grade within an industrial building.  However, the table would become out of level by a few thousandths and fluctuate over time.  As a result, the slab was reportedly torn out, some excavation below subgrade occurred, and an 18-inch independent slab (with #5 bar @ 12" OC) was poured.  I've been informed that the subgrade consists of relatively fine sand fill, and was compacted prior to slab construction.  Nevertheless, the problem persists. As a demonstration, a small forklift was positioned on a corner of the slab and it temporarily settled 0.007± inches.  
  
Some additional information:
- Slab/mat measures 20'x16'x1.5'
- Assembly table weighs approx. 3 tons
- Facility has experienced temporary flooding of the shop floor in recent months.
- Overhead cranes and forklift traffic are present in the area of the table.

I've been asked to evaluate why the slab continues to move even after replacement.  Since the slab will remain in place (for now at least), my observations and testing capabilities are limited.  To determine the soil and water conditions present beneath the slab, cores alongside the slab are planned, with hand-augered sampling below.      

Has anyone experienced similar scenarios?  Can this small of movement be stopped, and by what means?  Helical piers? Polymer injection?

Thanks for your time.  I've been a long time lurker and am thankful for everything I've learned over the years on this site.    


     

RE: Problematic manufacturing slab/mat movements

The earth is not a static mass.  This magnitude of movement is inevitable.  If it had been founded on piles, the problem would have been lessened.  I doubt there is much that can be done with the existing slab sitting on the ground.

RE: Problematic manufacturing slab/mat movements

This is a prime example of measuring with a micrometer, marking with a crayon, and cutting with an axe.

If you think you can accurately measure 0.007" consistent elastic movement in a fine sand fill...well, you're fooling yourself.

If you have an application that is so critical, then the foundation mass must be increased to several multiples of the activity mass.

You could consider injection of a chemical stabilization grout or an expansive foam injectant. Either will stabilize your condition.

RE: Problematic manufacturing slab/mat movements

(OP)
Thank you hokie66 and Ron.
I had my doubts that such small movements could be avoided.  Wouldn't the movements have been slightly smaller had the base materials consisted of a well-graded crushed stone, which has a higher coefficient of subgrade modulus?  Thanks again.   

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources