MEP Dead Load Allowances
MEP Dead Load Allowances
(OP)
I have a project to install solar panels on the roof of an existing municipal swimming pool building. The as-built drawings of the pool indicate that the dead load used for design of the roof OWSJ's was 20 psf.
Based on the construction of the roof system, I come up with a dead load of 12.3 psf for the roof construction. This means the EOR used an MEP allowance of about 7 psf.
This seems to be a bit too much for this building. There is ductwork, electrical (lights), and fire sprinkler system hanging from the joists. There is no ceiling (open to roof deck).
If this were an office building, I would typically use 10 psf for MEP. However, there is very little hanging from the roof, so I am inclined to use something around 3 to 5 psf for MEP.
I searched high and low for some kind of guidelines for MEP allowance but found nothing, other than references to 10 psf for office buildings. Anyone have rules of thumb that they use?
Based on the construction of the roof system, I come up with a dead load of 12.3 psf for the roof construction. This means the EOR used an MEP allowance of about 7 psf.
This seems to be a bit too much for this building. There is ductwork, electrical (lights), and fire sprinkler system hanging from the joists. There is no ceiling (open to roof deck).
If this were an office building, I would typically use 10 psf for MEP. However, there is very little hanging from the roof, so I am inclined to use something around 3 to 5 psf for MEP.
I searched high and low for some kind of guidelines for MEP allowance but found nothing, other than references to 10 psf for office buildings. Anyone have rules of thumb that they use?






RE: MEP Dead Load Allowances
BA
RE: MEP Dead Load Allowances
Sorry. I assumed this was known. Mechanical, electrical, plumbing.
RE: MEP Dead Load Allowances
RE: MEP Dead Load Allowances
I have an old SBC 97, Appendix A Dead Load table:
mech duct allowance= 4psf
If you know exactly where the existing sprinklers, lights, etc. are located and what exactly they are, than you can calc their weight and reactions pretty precisely. Then you can probably treat this as a more exact point load analysis when it comes to the racks for the solar panels, rather than doing everything in terms of uniform PSF. Actual weights are allowed to be used in most building codes rather than pre-construction uniform dead load allowances..
HTH,
Andrew Kester, PE
Florida
RE: MEP Dead Load Allowances
Actually, you're right. For this particular project, I can figure out what the actual dead load is. It turns out to be about 3 psf for the MEP.
However, this project got me thinking about the design process and why the EOR used 20 psf for this building. So, my question is probably more of a general nature versus my specific project.
RE: MEP Dead Load Allowances
Besides, somebody may come along one day and try to put solar panels on the roof.
RE: MEP Dead Load Allowances
15-20 psf for roof dead load allowance on commercial buildings is common in my experience (mostly in Florida and SE), I'd like to know what others are using too...
HTH,
Andrew Kester, PE
Florida
RE: MEP Dead Load Allowances
I do not put toilets on the roof, so, no plumbing loads.
Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask
RE: MEP Dead Load Allowances
In my neck of the woods, engineers are adding considerably more than that to include ballast on roofs with insulation not fully secured to the deck. It does not pay to be nigardly about the assessment of dead load because the money saved is peanuts compared to the money required to rectify the design in the event of some unexpected additional load in the future.
For a swimming pool, an allowance of 30 psf dead load is not unreasonable, considering the possibility of additional mechanical requirements in the future.
BA
RE: MEP Dead Load Allowances