INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pipeline Load Reduction Due to Trenching

Pipeline Load Reduction Due to Trenching

Pipeline Load Reduction Due to Trenching

(OP)
Ref.: DNV-RP-F109 (Oct 2007), sec 3.4.5 (EQs 3.21 & 3.22)

My case: modeling of subsea pipeline in a trench

Question: I understand in case distance of pipeline from either trench sides/walls is more than 3D (D is pipe outside diameter) the load reduction due to trenching is not considered. Is it correct?
 

RE: Pipeline Load Reduction Due to Trenching

Yes, it's correct.
In this case you've three different options:
- don't consider the trench (very conservative approach)
- use another standard like Danish Submarine Pipelines Guidelines (very old standard)
- use a software to simulate hydrodinamic flow inside tranch (like AGA).

 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources