Sorry for the re-post, but this got kicked out of the structural engineering section. It got kicked out before I had a chance to read any of the responses.
I've been running a job in CA for several months now. I was involved in the design peripherally, but when the project engineer left the CA got dropped in my lap. It is an existing building renovation and addition, and there are a number of things that I have noticed that seem odd in the sense that I'm surprised that this is the way a project engineer of this person's caliber left this project.
I have been looking at these areas as I have a chance to and can generally rationalize my concerns away, but am still surprised at the approach. Should I be rigorously verifying all of these conditions that concern me or look odd(which I've been trying to do by either analysis or rationalization) or assume that the project engineer (with much more experience than I have, I would add) has it right and just go on my merry way?
It's been a real drain on my time and I'm not getting any relief on other projects. I just wanted to get some input on this.
I've been running a job in CA for several months now. I was involved in the design peripherally, but when the project engineer left the CA got dropped in my lap. It is an existing building renovation and addition, and there are a number of things that I have noticed that seem odd in the sense that I'm surprised that this is the way a project engineer of this person's caliber left this project.
I have been looking at these areas as I have a chance to and can generally rationalize my concerns away, but am still surprised at the approach. Should I be rigorously verifying all of these conditions that concern me or look odd(which I've been trying to do by either analysis or rationalization) or assume that the project engineer (with much more experience than I have, I would add) has it right and just go on my merry way?
It's been a real drain on my time and I'm not getting any relief on other projects. I just wanted to get some input on this.





RE: Question on Ethics
RE: Question on Ethics
RE: Question on Ethics
First, have you brought your concern to the attention of your supervisors in the company? That is probablty a good move, if you're sure there's a concern.
Second, I'd say you're doing the right thing, checking items that you find suspicious. However, if your doubts are always reassured, perhaps this would lead you to be less suspicious.
RE: Question on Ethics
RE: Question on Ethics
This is especially true for existing building renovations where there are always hidden items that are not uncovered until the CA stage.
If you think there's something wrong with the design, then fix it. It is now your responsibility. If you're an EIT, then it is your bosses responsibility.
RE: Question on Ethics
The other engineer left after design was complete, but before CA started. There was no design to "see through". I'm only stumbling upon things during times where I am reviewing shops, responding to RFI's, or just perusing the drawings for my own benefit.
Just because I think there's an issue doesn't necessarily mean there is........... and that is the crux of my question. Do I need to go and look at everything that looks off to me or can I make a good faith assumption that unless something looks downright wrong that the design engineer has things right? If I had all the time in the world I wouldn't even ask the question, I would just review everything, but I live in the real world and don't have that much time.
RE: Question on Ethics
I could offer general comments about picking up a ball of chalk from another guy you'd have expected better of...
However, given your industry, I wonder if there are legal or similar issues such as those B16A2 brings up, so I'll leave it to your fellow structural's unless you want general comments.
What is Engineering anyway: FAQ1088-1484: In layman terms, what is "engineering"?
RE: Question on Ethics
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Question on Ethics
Don't let the experience issue deter you from raising questions and eliciting proper response from your supervisors. Remember, his "project engineering" could result in a liability to your company that the principals need to know and they need to know now, not later. If your concerns are unfounded, so what..at least you got them out there and maybe learned something in the process. If they are well-founded, then you probably will have saved your company a lot of grief and ill-will.
Go do what you think is right...you're usually on target.
RE: Question on Ethics
This is not an uncommon situation, and I have been in it several times. My principle has always been that to oversee construction, I have to understand and agree with the design.
RE: Question on Ethics
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Question on Ethics
RE: Question on Ethics
Your bosses should be able to ascertain the condition of the set. If they dont want to give you the time to recheck designs, then it's the risk that they're taking for you. I would move on and consider it another strike against the company... you are looking to leave right?
If something fails, your company gets sued. The EOR may not have been working in the best interest of your company if he was about to leave. IMHO, depending on the project, it could be a big risk.
RE: Question on Ethics
RE: Question on Ethics
RE: Question on Ethics
An expert is a man who has made all the mistakes which can be made in a very narrow field
RE: Question on Ethics
RE: Question on Ethics
You are a very competant engineer and if you are concerned with something then you should do with what you think is the ethical thing to do. Structural Engineers hold a specific duty of care to the community much the same as doctors, and if you pass off a concerning item as "I'm sure the project engineer looked at it" would be considered negligent. I am not having a personel attack on you, I find your posts on the structural engineering forum to be very insightful and display a great deal of knowledge.
I actually found myself in a position very similar to yourself early in my career (refurbishment job) and saw a colleague give advice which I can only describe as unethical. I was very vocal in voicing my concern that it actually led me to being laid off. Still to this day I do not regret anything that I did and maintain that I rather had been temporarily unemployed that be responsible for something which could potentially cost someone their life.
RE: Question on Ethics
RE: Question on Ethics
RE: Question on Ethics
For example, engineer vs. manager; doctor vs. insurance company; soldier vs. politician
I am just wondering with issues like the BP spill, if engineers are forced to make decisions that they would normally wait to make until they had more information.
I myself have been in situations where I have almost no information, yet am supposed to extrapolate conclusions to a very fine edge. If I don't respond the company looks bad and the client will search for another engineer to get the answer they want.
Are we becoming less intrested in the public good and more intrested in client satisfaction?
RE: Question on Ethics
I can sort of imagine some guy saying, "You can't put it here; the ground's too squishy and we haven't completed a proper foundation," and the project manager saying, "But the church wants its Tower of Pisa up, ASAP!" Note that the tower was already leaning by the time the third floor was erected, and subsequent floors are built on a tilt to compensate for that initial tilt.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Question on Ethics
Pressure to launch the challenger was huge. Program goal was a flight every week or 2.
http://
In engineering, time is literally money, often large amounts. An engineer is typically near the apex of a pyramid of committed (presently or in the future)material, cash and labor resources. A production leader was kind enough to invite me to the shop floor and break down the cost of downtime on his idle 10+/- person line (~$10/min, bldg overhead not included)for me before sending me off to solve his problem toute suite (drove around the corner to hose shop for fittings, sketched fixture for brazer, <30 min. The cost of capitol needs to be considered as well.