×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Potential issues with Large Diameter Sewer, Low Design Flows?

Potential issues with Large Diameter Sewer, Low Design Flows?

Potential issues with Large Diameter Sewer, Low Design Flows?

(OP)
I'm in the process of redesigning a sewer system for a small commercial project due to a utility conflict.  Original intention was to extend a 10" public sewer main along street frontage and tap 6" service off of it for project; this has been scrubbed due to utility conflict blocking 10" main alignment.

New plan is to provide a site service using a pre-existing sewer stub (on other street frontage).  Contractor would like to use the 10" pipe that they already have.  Est. peak flows for the line are 150 gpm max...with average flows more likely in the 20 gpm range.

I'm concerned that running such low sewer flows through a large diameter line (10" at 1/8"/ft) will lead to clogging of the service line.  If I were designing such a system from scratch, I'd use a 4" or 6" dia. line.

Running it through Mannings for 6" I get:
1.9 fps @ 20 gpm (18.5% full; marginal but close to 2 fps min)
2.3 fps @ 40 gpm (26% full)

for 10":
1.7 fps @ 20 gpm (10% full; slow...)
2.1 fps @ 40 gpm (13% full)

Anyone have any thoughts or input?  Thanks.

RE: Potential issues with Large Diameter Sewer, Low Design Flows?

There is usually a minimum requirement that service sewers (building sewer to public sewer) have 1 to 2% slope.

RE: Potential issues with Large Diameter Sewer, Low Design Flows?

Require the contractor to use 4"/6" sewer pipe and get a credit from the supplier for the 10".  If the contractor can't get a credit, then the owner pays for the 10" pipe.  There should be a credit change order for the contractor not having to install the sewer in the public right-of-way.

RE: Potential issues with Large Diameter Sewer, Low Design Flows?

How long does the peak flow last. Check the Velocity at peak flow, and, if this is more than 3.0 fps, should be adequate to resuspend the deposited material.

RE: Potential issues with Large Diameter Sewer, Low Design Flows?

just because a contractor wants to save money doesn't mean you should agree. the long term O&M costs to clean out the clogged sewer every 6 months will be paid by the owner, not the contractor and they will blame you for it.

RE: Potential issues with Large Diameter Sewer, Low Design Flows?

(OP)
In the end I've required a switch out to 6", sticking with the known vs. the unknown.  Project owner would definitely not thank us for saving a couple thousand bucks (potentially) if the sewer is clogging down the road.  

For this building, peak flows would have only occurred one day per week, so interim accumulation could have posed a problem.  

Thanks all for your timely and informative comments.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources