HTRI Shell Geometry Output
HTRI Shell Geometry Output
(OP)
Hi, anyone could help to understand the meanning of this part of the output summary given by HTRI software, when it says (Shell geometry) Series 1 and Parallel 2, i think this is i need 1 row of 2 equipment in parallel. How if Series 2 and Parallel 5?





RE: HTRI Shell Geometry Output
2 series 5 parallel basically means 5 next to each other with one exchanger stacked on top of each (10 total). you'd have 20% of the flow going through each and then going through the exchanger on top.
RE: HTRI Shell Geometry Output