Help me to get: QW-200.4 Combination of Welding Procedures
Help me to get: QW-200.4 Combination of Welding Procedures
(OP)
Hi
Dear all members:
I've got problems understanding the following section !I would deeply appreciate it if someone help me out explaining the fllowing paragraph with picture.Thanks in advance.
b)For GTAW, SMAW, GMAW, PAW, and SAW,or combinations of these processes, a PQR for a process recording a test coupon that was at least1⁄2 in. (13 mm) thick may be combined with one or more other PQRs recording another welding process and any greater base metal thickness. In this case, the process recorded on the first PQR may be used to deposit the root layers using the process(es) recorded on that PQR up to 2t (for short-circuiting type of GMAW, see QW-404.32) in thickness on base metal of the maximum thickness qualified by the other PQR(s) used to support the WPS. The requirements of Note (1) of QW-451.1 and QW- 451.2 shall apply.
Dear all members:
I've got problems understanding the following section !I would deeply appreciate it if someone help me out explaining the fllowing paragraph with picture.Thanks in advance.
b)For GTAW, SMAW, GMAW, PAW, and SAW,or combinations of these processes, a PQR for a process recording a test coupon that was at least1⁄2 in. (13 mm) thick may be combined with one or more other PQRs recording another welding process and any greater base metal thickness. In this case, the process recorded on the first PQR may be used to deposit the root layers using the process(es) recorded on that PQR up to 2t (for short-circuiting type of GMAW, see QW-404.32) in thickness on base metal of the maximum thickness qualified by the other PQR(s) used to support the WPS. The requirements of Note (1) of QW-451.1 and QW- 451.2 shall apply.





RE: Help me to get: QW-200.4 Combination of Welding Procedures
As an example,
I have a PQR qualified on .5" thick P1 mat'l using the GTAW process, with PWHT. I have another PQR qualified on 1.5" thick P1 material, using the SAW process with PWHT.
I have a job where I must weld 2" thick material and I cannot back gouge so I must make the weld from 1 side.
I can combine the PQR's and make a one sided weld using the GTAW process for the root layers, and fill and cap with the SAW process . The completed joint will be PWHT'd.
RE: Help me to get: QW-200.4 Combination of Welding Procedures