INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Electrical Substations

Electrical Substations

Electrical Substations

(OP)
I am reviewing information for electrical Step-up substations (From multiple Generators, collected and delivered to the Substation where it is stepped up to Utility or ISO required Voltage) and trying to determine if there is a standard as to the costs devoted to both the low voltage and high voltage sides of the substation. Is there anything which lists approximate percentages of costs on the low and high side of the substation? I am trying to determine if the costs are fairly stated.

I appreciate any help,

Franks

RE: Electrical Substations

I don't believe that there can be any useful generality on the percent of costs on the low and high side.  It depends mostly on what kind of switching configuration, number of lines, and protection are needed in each.  A large part of the cost is the transformer connecting the two.
 

RE: Electrical Substations

Adding to jghrist's list, the respective voltages on HV and LV sides and the type of switchgear (air, GIS, etc) will have a significant impact.
  

----------------------------------
  
If we learn from our mistakes I'm getting a great education!
 

RE: Electrical Substations

Only way to make a "fair" assessment is have design documents with necessary details and have a few competent contractors bid the work. Ask them to itemize the line items you want them to be.  Even after that they will be all over the place, except the total may be somewhere in the ball park.

All these takes time and money.

Rafiq Bulsara
http://www.srengineersct.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources