Earned Value Method
Earned Value Method
(OP)
Dear Friends,
Could anyone kindly help me with my questions?
1.Why in the US EVM method is compulsory for projects with high capital cost?
2. Is earned value , the best way for controlling construction work in case of project control?
Regards,
Soheil Pak
project engineer
Could anyone kindly help me with my questions?
1.Why in the US EVM method is compulsory for projects with high capital cost?
2. Is earned value , the best way for controlling construction work in case of project control?
Regards,
Soheil Pak
project engineer





RE: Earned Value Method
As far as I know, EVM is not compulsory in the US unless the client requires it. Who is demanding it?
It's certainly a good method, but in my work it comes up very infrequently...
Good on ya,
Goober Dave
RE: Earned Value Method
But, that's all just shuffling numbers. YOU as the program manager controls the program, not the EVM system, which is a tool, just like your calculator.
And, no, it's not "compulsory," although most companies' program management processes probably require it. However, most companies don't really follo their own processes.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Earned Value Method
RE: Earned Value Method
RE: Earned Value Method