INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Trunk water mains

Trunk water mains

Trunk water mains

(OP)
I have seen conflicting specifications regarding whether shop drawings or laying schedules follow the approved geometry drawings of trunk water mains. Any thoughts on this?

RE: Trunk water mains

why would you approve them if they didn't? Contractor had better have a good reason for changing your alignment and the engineer had better agree on it. Otherwise, might as well let the contractor design the waterline.

RE: Trunk water mains

(OP)
I confess to be at a loss with your answer. The question is, and I apologize if it was not clearly understood, after the geometry, what comes next? the laying schedule or the shop drawings. I've read specs. that indicated that the laying schedule follows the geometry, then shop drawings come next; other specs. indicate otherwise, shop drawings after the geometry then the laying schedule.
 

RE: Trunk water mains

All of the pipelines we have done have had the laying schedule included as part of the shop drawings.

RE: Trunk water mains

The contract drawings hold. He agreed to the installation as shown on the plans and specs.

I'd reject their submittals that suggest otherwise.

If they are modifying the alignment. If they are, a change order should be processed. Less pipe=less $$$$$.



RE: Trunk water mains


Agreee with coloeng.


SUBMITTALS
Submittals shall be made by the Contractor in accordance with the procedures set forth in Section 105 and as described below:
A. Provide a construction schedule for approval that includes the sequence of installation of casings, pipelines and manholes. Provide a laying schedule (on the Drawings) that show necessary deviations from the Drawings due to specific utility conflicts discovered during required exploratory excavations.
B. Submit each manufacturer's and/or supplier's certification(s) attesting that the pipe, gaskets, manholes, castings, and appurtenances meet or exceed the specified requirement.  

RE: Trunk water mains

(OP)
I also agree with coloeng. But if an approval order is to follow: geometry; shop drawings; laying schedule, sounds practical.   

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources