INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

AASHTO Article 10.24.6.1 - Fastener Sealing

AASHTO Article 10.24.6.1 - Fastener Sealing

AASHTO Article 10.24.6.1 - Fastener Sealing

(OP)
AASHTO Article 10.24.6.1 gives guidance on fastener spacing for "sealing against the penetration of moisture in joints".  Ohio DOT's concrete deck haunch starts at the bottom of the top flange and proceeds to the deck at an angle.  This means that the outside (above the top flange) top flange splice plate is embedded in concrete.  Does anyone have any information as to whether, in this case, we must still adhere to AASHTO Article 10.24.6.1?  Does anyone know of any discussion or commentary on the subject?  ODOT does not have any discussion in the Bridge Design Manual.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread