INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

exporting

exporting

exporting

(OP)
Hi, I have been trying unsuccessfully to pass a report I get in primavera to excel...

What I mean is that in p3 when I ask in tools tabular reports resources loading...
I get the report in primavera look, and I can save it in rft...but does anybody know how can i get in in a format where I can use it in excel?

What I really want in to have in excel a list of the resources and what quantities per month are going to be used...

And the same but instead of the quantities, the cost...

As I said, I can get them in primavera look and I can save them as rft, but then I am stuck

thanks,

Cesar Baquerizo

RE: exporting

Hi Cesar,
Try the following:
Click on modify report and then the Format tab. Then click in 'Export report in CSV format to file' and give it a name (or accept the default). Take the option 'View on Screen' and your file should be opened into an Excel file. You will have to do a certain amount of formatting, but this can be saved as an Excel file.
Hope this works for you,
Rentaplan

RE: exporting

(OP)
Hi, when I am in the format tab, I cant see that option...

A friend of mine use to do it all the time in my primavera, but he is out of the country and I cant ask him how he did it...

Any ideas?

thanks,

Cesar Baquerizo

RE: exporting

Hi again Cesar,
The menu Tools/Tabular Reports/Resource/Loading reveals a number of standard resource loading reports. If you select (single click/Modify or double click)any one of the reports and then click on the Format tab, you should see 2 options on the left side, 'Generate report in P3' and below it 'Export report in CSV format to the file'. If you don't have this option then I don't know which version of P3 you're using!
I hope this is of some use.
Regards,
Rentaplan

RE: exporting

Hi Cesar!

You should find it there.  I confirmed it.

Click:  Tools, Tabular Reports, Resource, Loading
Choose a report and click:  Modify
Click Format Tab
You should find "Export in CSV format..." on the second line.

Best regards,

Jorge

RE: exporting

Hi. I need some help on how to export into Excel, a P3.1
file.
This is a Schedule of values tabular file in P3 and
how do you export the 'report writer' to a Excel file.

Thanking you for this help.

SSS  

RE: exporting

Use Tools/Tabular Reports/Resource/Tabular and in the Timescale window specify .WK1 for your extension.
Craig

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources