INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ICPR model setup question

ICPR model setup question

ICPR model setup question

(OP)
I am a relatively new ICPR user, and had 2 questions regrading model setup for a project.  The project only has one basin, and there are 2 subareas.

In existing conditions, the site is undeveloped (i.e., no pipes, channels, ponds, etc.).  Therefore, I have 2 nodes (one for each subarea) - and I am trying to determine how to model the peak flow for the basin without any links.  Basically, I am trying to figure out how to set up the exsiting conditions model in ICPR to produce the same results as I would get using the ADDHYD command for the subareas in TR-20 (i.e., how to get a peak flow for the composite hydrograph of the basin without routing the individual subarea peak flows).     

My other question (for the proposed conditions model) is similar in nature. I have a pond in one subarea (Subarea 1),and a small storm drain system in Subarea 2.  I have also added a boundary condition.

The Tt in the storm drain system (which is quite small) has already been incorporated into the TR-55 Tc calcs.  Again, I am trying to determine how to ADDHYD the routed Subarea 1 hydrograph with the unrouted Subarea 2 hydrograph.

Any help would be greatly appreciated.  

     

RE: ICPR model setup question

Existing conditions- simply create one downstream boundary NODE and attach multiple BASINs to it.

Proposed conditions-
IF you are modeling the storm drain system in ICPR (entering each inlet, pipe etc.), do not include it in the Tc or Tt.

As far as building the network, from what you describe, a minimum would be:
1. a downstream boundary NODE with the unrouted BASIN attached..
2. a NODE representing your pond.
3. a BASIN attached to the pond (or muliple inlet NODES with subBASINs and pipe LINKS to the pond)
4. LINK(s) from the pond NODE to the boudnary NODE representing the pond outlet(s).

RE: ICPR model setup question

(OP)
Thanks so much...I'll give that a try.  It makes sense, I didn't think about attaching basins to the boundary node.  I was creating additional nodes for all basins, then having problems determining how to link them.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources