INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

H-Pile set in drilled shaft (not driven)

H-Pile set in drilled shaft (not driven)

H-Pile set in drilled shaft (not driven)

(OP)
I'm looking for some guidance or information on the design and installation of steel H-piles set (not driven, but placed) in a drilled shaft that is then filled with concrete.

Any literature or specifications out there?  Any experiences?

Thanks!

RE: H-Pile set in drilled shaft (not driven)

I would call this a "plunge column" and you should be able to find info by using google.

Of course accuracy of setting is the crucial point and this will be helped if there is a bored pile casing at the upper level.

But some more info would help. Is this a basement construction? Is there a length of "empty bore" after completion of the bored pile and H-Section?

 

RE: H-Pile set in drilled shaft (not driven)

What is the purpose of the pile?

RE: H-Pile set in drilled shaft (not driven)

Why wouldn't the design be similar to that of a drilled shaft design?

www.PeirceEngineering.com

RE: H-Pile set in drilled shaft (not driven)

H-pile set in concrete is very common in the New York City building code; it is known as the core steel reinforcement within a caisson.  Typically, a casing is used and the core beam set and then tremie concreted.
Also, this type was used in Rhode Island for soldier piles with pre-cast concrete lagging along the Amtrak corridor.  My understanding is that the drilled shafts were augered with a special rig that injects the concrete on the way up; then the H-pile is pushed into place while the concrete is fresh.

RE: H-Pile set in drilled shaft (not driven)

Codes may require a minimum length for bearing piles.  If bedrock is too shallow so that driven piles cannot reach the minimum length, a drilled rock socket may be required in order to achieve the minimum pile length.  After the rock socket is drilled, the pile is set and the entire hole is backfilled with concrete.  The design could be done by several methods.  The pile could be designed as a caisson (drilled shaft), a micropile, a friction pile (bonded to the sides of the rock socket), an end bearing pile, or a  combination friction/end bearing pile.  Since the pile is not being driven, the allowable compressive stress in the pile should be higher than for a driven pile.  Obviously, an auger would not work well if you need a rock socket.  If there is no rock, there isn't any reason to auger the hole unless someone is worried about noise or vibrations.

www.PeirceEngineering.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources