INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Laterally loaded pile + excavation

Laterally loaded pile + excavation

Laterally loaded pile + excavation

(OP)
Hello all!

I have a situation. There is a 45deg excavation near the existing sign board which is on a short pile. Just wondering how far digging can go without damaging the pile?

Appreciate for help.
 

RE: Laterally loaded pile + excavation

With the proper subsurface information, your project geotechnical engineer can answer the question.  There is no short answer.

RE: Laterally loaded pile + excavation

There are two things you have to take into account:
1.It should bigger than 5B B=diameter of pile (better to see some literature)
2.Vibration effect caused of your digging

RE: Laterally loaded pile + excavation

GeoPaveTraffic is right.  
The following questions need to be answered before the geotechnical engineer can give an answer:
1. what kind cohesive soil it is, fill, soft clay, firm clay, stiff clay or hard clay?
2. where is the ground water regime?
3. how deep is the excavation?
4. how long will it open?
5. what is the season for construction?
6. is the original design sono-tube allow for short term side exposure (structural engineer's verification)?
7. is the excavation to be backfilled?
8. any surcharge/vibration/slope near the site?
9. other considerations may affect the excavation, say underground utilities, previously man-made trenches or buried features, etc.?

If the excavation is really shallow, in the good soil, temporary, no high water table, to be backfilled right away, you probably worry little.  If some or all unfavorable factors kick in (most cases), you will need a full review by an geotechnical engineer.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources