When new drums of 11kV Cables arrived at site, what test should be done?
When was the last time you drove down the highway without seeing a commercial truck hauling goods?
Download nowINTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
What Test should be done for New Cables ?
|
RE: What Test should be done for New Cables ?
RE: What Test should be done for New Cables ?
Rafiq Bulsara
http://www.srengineersct.com
RE: What Test should be done for New Cables ?
2nd option, VLF test, energize, then do on line PD testing to establish baselibe data for future on line PD testing. If getting a shutdown is near impossible at your facility this may be your best option.
3rd option, VLF test. If you do not plan on doing any regular testing in the future a VLF test will suffice. Not the best option but the cheapest.
RE: What Test should be done for New Cables ?
I didn't know that the VLF test and PD(what's that?) is for establishing the baseline data......
What is the data for? What's the theory behind?
RE: What Test should be done for New Cables ?
PD: Partial Discharge
My advice for new cable is to follow the manufacturer's recommendations for field testing.
Cable testing is a controversial subject and to some extent the answer will vary depending on the type of cable insulation.
David Castor
www.cvoes.com
RE: What Test should be done for New Cables ?
RE: What Test should be done for New Cables ?
The baseline data is for condition assesment. There have been some excellent threads here in the past.