We have: Alternative I: Two generating units of 105 MW each initially for total design discharge of 30 cumecs and Net head of 820 m.
Due to transportation constraints of bulky machine, we are exploring the alternative II of having smaller but more no. of units.
So what should be the minimum discharge for each unit? Some standard says 10% while other says (20-25%). Can you all enlighten me on it? I would appreciate.
Good day to you all!
Due to transportation constraints of bulky machine, we are exploring the alternative II of having smaller but more no. of units.
So what should be the minimum discharge for each unit? Some standard says 10% while other says (20-25%). Can you all enlighten me on it? I would appreciate.
Good day to you all!
"Common sense is genius dressed in its working clothes." -- Ralph Waldo Emerson






RE: No. of Generating Units
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: No. of Generating Units
Alan
"The engineer's first problem in any design situation is to discover what the problem really is." Unk.
RE: No. of Generating Units
Can you enlighten??
"Common sense is genius dressed in its working clothes." -- Ralph Waldo Emerson
RE: No. of Generating Units
RE: No. of Generating Units
"Common sense is genius dressed in its working clothes." -- Ralph Waldo Emerson
RE: No. of Generating Units
Alan
"The engineer's first problem in any design situation is to discover what the problem really is." Unk.