INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME B31.3- MPI/LPT on Process Piping Butt Welds

ASME B31.3- MPI/LPT on Process Piping Butt Welds

ASME B31.3- MPI/LPT on Process Piping Butt Welds

(OP)
Dear Friends

Base Material - CS & SS - Process Piping - Dia range from 2" to 6". Weld Porcess - GTAW(Root) SMAW (the rest ).
Based on what I've understood above code does not call for MPI/LPT on Butt/Girth Welds. I've done RT as as required in Project approved NDT Plan. Can some one guide to the code section which call for MPI/LPT? I need your guidance urgently. Thanks

RE: ASME B31.3- MPI/LPT on Process Piping Butt Welds

B31.3 does not require MPI (MT) nor LPT (PT) on butt/girth welds. Refer to Clause 341.4.1 of ASME B31.3 as this is where examination requirements for piping are specified.

Did your clients specifications require MT or PT ?

 

RE: ASME B31.3- MPI/LPT on Process Piping Butt Welds

(OP)
Hi, Rneil, Yes mentioned in the latest ISO Drawings. Job concluded based on Rev 3 which only require to comply with ASME B31.3.But Rev. 4 calls for 20% RT(same as in earlier rev.& Done) + 5%MPI on butt welds
Reinstament done and commissioning completed.
That's the reason. I want to confirm if MPI requirement required according to B31.3.Thanks for prompt reply

RE: ASME B31.3- MPI/LPT on Process Piping Butt Welds

While, there is no code requirement for MT on butt welds so if this requirement was issued by the client after the contract was awarded, you should go back to them asking for a change order and compensation.

I have never heard of a client asking for MT on butt welds before but there's always a first time.  Much more common to ask for MT on fillet welds (e.g., socket welds) - perhaps this was a mistake ?

RE: ASME B31.3- MPI/LPT on Process Piping Butt Welds

The Owner's new requirements constitute a change order. Simply clue them in as to the costs of compliance. I am sure you can come to a most profitable cost addition, assuming erection of new scaffolding, removal of insulation, removal of paint and repainting, etc. If the price is high enough, the Owner may rethink his Change.     

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources