INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

PMS & AGO loading facility

PMS & AGO loading facility

PMS & AGO loading facility

(OP)
Hello Good people,

I have this new project on my desk. It is a facility that accepts petroleum products from a cargo vessel, stores it in about 4 steel welded tanks, then disburses at a loading station to trucks.

I need some guidance, particularly book referals concerning the following:

The necessity for slop tanks and its requirements for design.

The truck loading arm design.

Foam extinguisher design

And finally, the necessary appurtenances for a PMS storage tank.

Regards

'Lekan

RE: PMS & AGO loading facility

Lekan, You've asked a big question and the small answer looks like this,



I'm afraid you'll have to Google "Petroleum Storage, Bulk Plants" to get the big answer.

**********************
"The problem isn't working out the equation,
its finding the answer to the real question." BigInch
http://virtualpipeline.spaces.live.com/

RE: PMS & AGO loading facility

(OP)
BigInch,

What can I say?

But thank you would do for now..........

Regards

'Lekan

RE: PMS & AGO loading facility

Condider spelling out the meaning of the acronyns PMS (petroleum measurement systems) and AGO.

API STD 2610 applies to the "Design, Construction, Operation, Maintenance, and Inspection of Terminal & Tank Facilities".

API PUBL 4688 addresses the "Temporary Treatment Options for Petroleum Distribution Terminal Wastewaters".

API RP 1595 covers the "Design, Construction, Operation, Maintenance, and Inspection of Aviation Pre-Airfield Storage Terminals"
 

RE: PMS & AGO loading facility

Lekan,  What I mean is try breaking down your work priority in smaller "Tip" bits, things we can give you tips on, and asking more specific questions, preferably one at a time, and we might be able to actually help you on specific issues.  Describing an entire bulk plant design would ... take a few pages and a lot of time.

**********************
"The problem isn't working out the equation,
its finding the answer to the real question." BigInch
http://virtualpipeline.spaces.live.com/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources