Smart questions
Smart answers
Smart people
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Member Login

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips now!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

Join Eng-Tips
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

LINK TO THIS FORUM!

Add Stickiness To Your Site By Linking To This Professionally Managed Technical Forum.
Just copy and paste the
code below into your site.

Partner With Us!

"Best Of Breed" Forums Add Stickiness To Your Site
Partner Button
(Download This Button Today!)

Feedback

"...Keep up the good work - excellent site - i'd been looking for something like this for ages !..."

Geography

Where in the world do Eng-Tips members come from?
XFEM (Structural)
1 Feb 10 3:50
Hello, i am an new bridge design engineer. usually we design the welded wide flange in bridge truss and girder member as 100% capacity, and let the fabricator gave the member weld. Lately another fabricator asked about how it should be welded?
And i was said that should be CJP [Complete Joint Penetration] and the fabricator bargain about the fillet, and PJP, and PJP with extra fillet.

All welded beams are Wide Flange with fy 355 MPa.

Question mark 1: can my welded beam welded like that?
note: several beam use 8-10 thick web at stringers.
      several beam use 12-14 thick web at crossgirders
      many beams use 8-30 thick web at truss members
      the tender code, i put was AWS D1.5
      the fabricator usually use AWS D1.1

Question mark 2: I saw D1.5 today. It said the force tension pararel to weld efective can be PJP. It is for truss beam right? not for girder/stringer/

My opinion: I would like to bargain to fabricator:
The girder and stringer should be CJP.
The truss beam <= 19 mm thick web can be PJP with double beveled, others thicker should be CJP.
Right?

Note the process is SAW.
Ron (Structural)
1 Feb 10 7:24
Several points come to mind.....

1. If you have an experienced mentor, let him deal with the fabricator the first few times while you attend and watch (assuming he is capable of doing so).

2. If the fabricator bid the project knowing it required CJP welds, he's just trying to get you to let him make more profit by doing PJP and fillet.  Those take less time and effort.

3. PJP welds are more difficult to inspect and test.  Further, you can create stress risers with PJP and fillets that do not exist with CJP welds.  This can be significant in fracture critical structures such as bridges.

4. If you allow the contractor to control the design, you will be putting yourself in a liability position you do not want.  You're the designer..you decide what is acceptable and what is not acceptable.  Yes, fabricators can design weldments through the shop drawing process, but you have to approve or disapprove them as the engineer of record.

Good luck.
bridgebuster (Civil)
7 Feb 10 9:19
In the northeastern US fillet welds are commonly used for built up girders, or as you wrote "wide flanges".  Truss projects that I was involved with that used closed box members were either CJP  or fillets, depending on the load in the member.

I agree with Ron, particularly item #2. He bid it; he bought it.
XFEM (Structural)
9 Feb 10 7:50
Thanks for the answers. We are in SouthEast Asia.

Likely not at my firm understands AWS and welding details, because we rare use built up members [primarily business in  buildings].

The fabricator wants to use less CJP because it need to be checked using UT not as PJP [according to D1.1, he said].
All the bridge fabricators use D1.1 in here. And they don't know the AWS D1.5M, even their experts from abroad.

Well, i think im go to use CJP, but the project is late, because of the new year. Can anyone gave me the minimum bargain proposal welding?

I think the Girder can be go to PJP, or fillet since it not the FCM. And the Truss should be assumed as FCM, and should be welded as CJP. Right?

The contract didnt say about CJP,PJP,etc. I just mention 100% capacity and must be according to D1.5
 
HgTX (Civil/Environmental)
9 Feb 10 11:19
This just hit something that drives me nuts about D1.5.  Because the inspection requirements for PJP, no matter how big the PJP, are no more than that for a fillet weld, people try to go for PJP just to escape the volumetric inspection.  The other side of it is that designers may specify CJP where only PJP is needed because they want more inspection.

We need a better way to inspect the PJPs so as to separate the design & inspection questions.  Okay, y'all, get working on that and report back to me next week!

Hg

Eng-Tips policies:  FAQ731-376: Eng-Tips.com Forum Policies

bridgebuster (Civil)
9 Feb 10 12:39
the tension members of the truss would be FCM.  

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close