×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Bridge Jacking Loads

Bridge Jacking Loads

Bridge Jacking Loads

(OP)
Lately it seems like I'm either involved with or hear about a lot of projects where it is necessary to jack a bridge superstructure off its bearings. This is generally to replace bearings or repair the substructure. So far, these have all been steel bridges, and the bearing types have varied.

I have noticed that sometimes the jacking load is very close to the reactions that were calculated. Other times, they are nowhere near.

I'm curious as to what other's experiences have been. How well, have you been able to predict both the force it takes to lift a bridge off its bearings, and the force that holds it there?

RE: Bridge Jacking Loads

A few points to make on your inquiry.  

1.  The most reliable load to estimate is the dead load.  Of course that will depend on modifications such as wearing surfaces that are placed.

2.  We will often use Live load in our calculations but then require that all jacking be done without live load.  Obviously the live loads vary from older structures to what we're required to use today.  

3.  I find that we can generally get within 5 to 10% of the original plans.  Typically I get disappointed as we approach 10% difference and begin to look for what might be the reason.

Regards,
Qshake
pipe
Eng-Tips Forums:Real Solutions for Real Problems Really Quick.
 

RE: Bridge Jacking Loads

The jacking load can also be greater than that calculated if you are trying to jack a beam next to another beam that is not being jacked simultaneously.  Diaphragms can cause you to start picking up load from the adjacent beam(s).  

www.PeirceEngineering.com

RE: Bridge Jacking Loads

JEmH,

When i design a steel or concrete bridge i normally left the provision for replace the pad bearings (Bigger Diaphragms). I place on drawings the place for each jack so the bridge does not rotate. The equipment for replacement is jacks plus some compressor, and it is no hard to get on site.

This addition to design it is not expensive, remember you need to voit overturning form seismic effects and it is going to be used something like once in 15 years.


If you do not do that it is not impossible perform the pad change. You have design a beam to place at girder bottom, perforate the slab for lifting cables and use a big capacity crane

Normally estimate dead load plus 5 to 10% it is enought.

Ajose

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources