INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Positioning of longitudinal welded pipe seams on a horizontal axis?

Positioning of longitudinal welded pipe seams on a horizontal axis?

Positioning of longitudinal welded pipe seams on a horizontal axis?

(OP)
I was asked a question on where does it specify in a code or standard where the longitudinal seam weld in a section of pipe is to be positioned when fabricating a piping system where the axis of the piping system is in the horizontal plane.  I remember being taught that it should be in the 9 O'Clock or 3 O'clock positions (horizontal plane and or 15 deg alternately from that axis) but I would like to see it in a Code or standard somewhere.  I was also asked that when fabricating a piping system in accordance with ASME B31.3 (Normal Fluid Service), is it incorrect to attach a weldolet where the hole cut in the pipe for the weldolet was cut through the manufacture's longitudinal seam weld.  What has happened in this instance is the orientation of the seam was fabricated in the piping system in the 12 O'Clock position and the weldolet needs to be installed on top in the 12 O'Clock position which of course involves cutting through the manufacture's longitudinal seam weld.  Does anyone know of some reference material or a section in the ASME Code that would give me the information I'm looking for?

RE: Positioning of longitudinal welded pipe seams on a horizontal axis?

These come down to good engineering practices.  Neither are a specific requirement of the code.

It would be good practice to stagger the next long. joint which is a requirement of the BPV code.

As far as cutting through the seam, I have never done it on a pressure system but have on a tank which is covered in API 650 Section 5.7.3.4 (when all other options have been exhausted).

RE: Positioning of longitudinal welded pipe seams on a horizontal axis?

In gas lines the 6 o'ck position is avoided to prevent possible corrosion from sustained contact with water and other liquids that might be running along in the stream.  

**********************
"Pumping accounts for 20% of the world's energy used by electric motors and 25-50% of the total electrical energy usage in certain industrial facilities."-DOE statistic (Note: Make that 99% for pipeline companies) http://virtualpipeline.spaces.live.com/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources