INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Die Electric Section for Well pump

Die Electric Section for Well pump

Die Electric Section for Well pump

(OP)
For electrical submersibl pump that will be installed inside deep water well ,  it ws specified to install
die electric section between the pump and the column pipe to prevent electrolysis . about 3m above the pump end we will installa check valve .

I don't know so much about the die elctric section , but I know why we need to install it.

Is it ok to install the DES after the check valve or it is better yo install it directly after the pump end ?

any information about the DES is highly appreciated ...

Thanks  

RE: Die Electric Section for Well pump

'Dielectric'.

Sorry can't help with the installation question.
  

----------------------------------
  
If we learn from our mistakes I'm getting a great education!
 

RE: Die Electric Section for Well pump

I would make the decision based on possible water hammer at the check valve. Will your dielectric section withstand water hammer as well as the metallic piping? Is the dielectric section resilient enough to mitigate water hammer somewhat?
 

Bill
--------------------
"Why not the best?"
Jimmy Carter

RE: Die Electric Section for Well pump

The purpose of the dielectric is to prevent galvanic action between metalic pipes made of different materials, if they are placed in an electrolytic medium (water typically). In other words, you need the dielectric if and where you're switching from one type of metallic piping system to another.  The metal with the higher potential becomes the anode (which corrodes) and the lower becomes the cathode (which remains unchanged).  A common example is when you switch from copper to steel pipe--the copper corrodes the steel.

So, in my opinion, the check valve location is (somewhat) irrelevant to the dielectric question...you need to look at the materials of the pump body, then the connected pipe, that of the check valve itself, and the "column pipe" or whatever.  See where it makes sense to put the dielectric fitting in based on the materials you plan on using and what will be cheaper/easier.  

 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources