INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Joints In Reinforced Concrete Slabs

Joints In Reinforced Concrete Slabs

Joints In Reinforced Concrete Slabs

(OP)
I have a large slab with a combination on longitudinal and contraction joints. Within the slab are a number of gullies and aqua channels. The channels are in line and approx. 2m long with a 2m gap between.

Q. should I make sure a joint in the slab runs along the line of aqua channels as if they are placed in the slab they will create a weak area. Or can this be ignored as the floor slab has already been divided into small bays (approx. 6X6m)
 

RE: Joints In Reinforced Concrete Slabs

I would make the joints at the 'sidewall' of the channels.  The channels will prevent the slab from moving and will be relatively 'fixed' at that location.

Dik

RE: Joints In Reinforced Concrete Slabs


A detail showing how the "gullies" and "channels" are to be constructed would help.
 

Ralph
Structures Consulting
Northeast USA

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources