Relieving platforms
Relieving platforms
(OP)
Does anyone have any good references of how soil pressures are determined below a relieving platform? I have an existing vault where the owner wants to place 10 feet of soil on top of it. I am proposing a relieving platform with piles, but wanted to know how wide I should make the platform in order to prevent an increase in soil lateral load pressures on the existing vault structure. i.e. how do I prevent additional surcharge being imposed on the existing vault.





RE: Relieving platforms
RE: Relieving platforms
1. The top of the new structure would have to be closed to avoid additional loading to the top of the existing grease sump.
2. The additional lateral pressure should be uniform in nature, not varied.
3. The new structure will completely enclose the existing sump, so why not replace the existing, or just build a new one and bypass the original.
4. Where is the max watertable?
Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask
RE: Relieving platforms
If you don't want to add compressible layers, in an elastic behaviour view, FEM is the answer; model the slab with the structure but not the fill, then add the fill (or equivalent load) and the changes are the increases in pressures. If constant section, even 2D models can be enough.
RE: Relieving platforms
Probably my question is really the theory or methodology for calculating lateral pressure when you have a relieving slab (ishvaag, your comment hit on this). How far do I need to extend the slab beyond the existing structure edge in order to get zero additional lateral stresses (20 feet, 40 feet, 100 feet)?
1. The plan is to place a slab with compressible fill below the slab. The slab would prevent additional loading to the top of the existing structure.
2. I agree the additional pressure would be uniform ( but without a relieving slab). Is it possible for the additional pressure to be equal to zero if the slab is wide enough? or is there a method where the geotech calculates a lateral pressure based on a rotational movement of a soil block rotating and inducing lateral pressures beneath the relieving slab?
3. I may consider a secant or tangent pile wall to surround the existing structure and tie the tops with a slab (ring beam).
4. Water table is 30-40 feet below the existing structure.
RE: Relieving platforms
RE: Relieving platforms
RE: Relieving platforms