INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME B31.3-PWHT on the same joint twice

ASME B31.3-PWHT on the same joint twice

ASME B31.3-PWHT on the same joint twice

(OP)
Dear Friends
Process Piping - Carbon Steel Piping - 6" Sch XXS ( 21.9mm )- PWHT done on the same butt joint twice. RT done after 1st PWHT-It passed.Is it acceptable to ASME B31.3?
What harm done to the joint ( weld metal & HAZ ) undergone PWHT twice, in terms of Mechanical Properties.... etc.
Thanks

RE: ASME B31.3-PWHT on the same joint twice

You didn't mention the material as you know CS covers a lot of materials.
If your material is A106 no harm done.

Please comeback with the piping specification for a more definitive answer..

RE: ASME B31.3-PWHT on the same joint twice

The only issue should be if supplementary essential variables are being applied and QW-407.2 of ASME IX has to be invoked: the original PQR may not have achieved the requisite 80% of the total time at temperature.

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

RE: ASME B31.3-PWHT on the same joint twice

RT after PWHT is not required for carbon steel under B31.3. refer to 341.3.1 (a).  

RE: ASME B31.3-PWHT on the same joint twice

Rt may not be required AFTER pwht but it is still required if dictated by the code...yes?

RE: ASME B31.3-PWHT on the same joint twice

I think i see what you mean now Stanweld...it is not required again...sorry...

RE: ASME B31.3-PWHT on the same joint twice

(OP)
Hi, Friends
MATERIAL - ASTM A106 / ASTM A53 x 6" x 21.95mm.
Pls explain "QW-407.8(b)a change of more than 10% in the no of PWHT heat cycle following the welding cyscle"

Thanks

RE: ASME B31.3-PWHT on the same joint twice

Will you be flash welding the items?  If not, don't worry too much about QW-407.8

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

RE: ASME B31.3-PWHT on the same joint twice

(OP)
Steve
I don't get your points. Pls explain Thanks

RE: ASME B31.3-PWHT on the same joint twice

Look in QW-250 and identify where QW-407.8 is specifically invoked as a requirement.  

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

RE: ASME B31.3-PWHT on the same joint twice

(OP)
Dear Friends
Material - ASTM A106/A3
I've been going through ASME B31.3 Chapter VI- Try to confirm extent of MPI if any required beside RT/UT for Process Piping Butt Welds.
If MPI required, please advise respective section(s).

I've concluded RT as per ABS Rules.ABS Rules do not require MPI.
Thanks in advance.

RE: ASME B31.3-PWHT on the same joint twice

4872,
For MPI, refer to 341.4.3(b) and 302.3.3 (for castings).
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources