INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Piping Fabrication and Installation Plan

Piping Fabrication and Installation Plan

Piping Fabrication and Installation Plan

(OP)
Hello AhliMekanik,
 On Sept. 14, 2008 you wrote,
 
AhliMekanik (Mechanical) 14 Sep 08 11:22  
Hi pennpiper,

We are an EPC company that want to make a tie-in standard specification for our company. Maybe the title of this spefication will be divided, such as :
1) Design Specification for Cold Tie-in
2) Fabrication and Installation for Cold Tie-in.

Until now we do not have yet a project that having tie-in work, but we would prepare this procedure for our next project proposal.

I already sent you, Piping Fabrication and Installation Procedure. The outline of this procedure is :
- Scope
- Reference
- General
- Storing and Protection from Demage
- Preparation and Fabrication
- Welding
- Heat Treatment
- Assembly and Installation of Piping
- Examination
- Pressure Test
- Flushing
- Tables and Figures
- Appendices.

Thank you with your kind attention.

Best Regards,
Ahli Mekanik  


Could you send me a copy of this procedure. I have a general work plan for piping fabrication and installation A/G and U/G, but am looking for something with more detail and content.

Thank you for you time,
 Joe
 

RE: Piping Fabrication and Installation Plan

I must confess that since your first posting (September 2008) I have not given this much thought.  I just assumed you had gotten the information you needed and had moved on.  My error.

Now, I must ask you:
Do you currently have a "Design Specification" for normal new project work?

And

Do you currently have a "Piping Fabrication and Installation Specification/Procedure" for normal new project work?

If so then I feel that these documents will also cover the issues related to "Cold Tie-Ins" when supplemented with the Planning guidelines I gave you in September 08 (see below).

Tie-In Planning (Activity - Responsibility)
1.    Identify each Tie-In(s) schematic location on P&ID - Process Engineer
2.    Review with Piping - Process & Piping Design
3.    Create a Tie-In Index (or List) with key information about each Tie-In - Piping Design & Process Engineer
4.    Review with Client - Process Engineer
5.    Go to the Field to locate physical point of Tie-In - Piping Design/Process
6.    Meet with plant personnel and review Tie-In requirements - Piping Design, Process, Plant Operations, Safety
7.    Discuss different types and configurations of Tie-Ins - Piping Design, Process and Plant personnel
8.    Establish physical Tie-In location point and type - Piping Design & Plant Personnel
9.    Define if the line can be shut –down, when, how long, draining, depressurizing, steam-out and other safety issues - All personnel
10.    Visually inspect the existing pipe.  Are more extensive tests needed to determine condition and suitability for the Tie-In - Piping Design and Plant personnel
11.    Mark or tag the selected Tie-In point - Piping Design & Plant Personnel
12.    Photograph the Tie-In point - Piping Design
13.    Draw sketch and take all required measurements - Piping Design
14.    Determine locations of all existing block valves, vents and drains - Piping Design
15.    Determine the location of all existing anchors and guides - Piping Design
16.    Based on selected Tie-In location and type determine if additional vents or drains will now be required - Piping Design, Plant Operations
17.    Include new vents or drains (if any) on sketch - Piping Design
18.    Insure that this process is followed for all Tie-Ins - All participants
19.    Get plant personnel to sign off on all data collected in the field - Piping Design & Process Engineering
20.    In the office modify the P&ID as required - Process Engineer
21.    Convert all field sketches into appropriate production drawings (Isometrics) - Piping Design
22.    Prepare a Plot Plan style "Tie-In Location Key Plan"
23.    Update the Tie-In List as required - Piping Design
24.    Review all Tie-Ins with Pipe Stress for effect on existing system piping and new system piping - Piping Design
25.    Finalize  (check, correct and approve) all Tie-In isometric drawings  -  Piping Design


Again, now every one who reads this and has been involved with Tie-Ins can add other steps based on there own experiences.  I encourage them to do just that.  It will only help.
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources