INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Boundary zone detailing

Boundary zone detailing

Boundary zone detailing

(OP)
Greetings

I 'd like to ask a question regarding boundary zone in special concrete wall as per UBC 1997.

1) Is that correct that the vertical reinforcement layout in boundary zone be controlled only by the requirement of confinement spacing?

2) Is it eligible to include the rebar outside boundary zone to compute interaction diagram as usual done by ETABS?

3) So is it correct to conclude that the boundary zone is just a matter of detailing not the matter of strength evaluation?

Please suggest.

Thank you  

 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.