INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

MR0175 & Cladding

MR0175 & Cladding

MR0175 & Cladding

(OP)
According to this spec : "Unless the user can demonstrate and document the likely long-term in-service integrity of the cladding as a protective layer, the base material, after application of the cladding, shall comply with NACE MR 0175"

Question : If we do a proper QA/QC during cladding installation, is that enough to satisfy above requirement? In this particular application cladding will be 316L and base material SA-516.

RE: MR0175 & Cladding

It all depends on application, on the rigidity (or flexibility) of the cladding specification, on the design of the cladded parts and the local technical slang used to describe the corrosion resistant protective layer applied on the carbon steel substrate (ie interchanging the expression of cladding with weld overlay, etc).
Personally I think that once the welding is involved in any way, there is no way you can demonstrate the soundness of your cladding, no matter how strong is your faith in your cladding process. Remember, to compromise the CRA barrier you need one only small weak point, not large internal area.
Consider this;- you might fabricate a stainless steel vessel, then build around it the carbon steel vessel tightly, then perform an explosive bonding of the internal vessel to the external one. Provided you do not make additional fabrication of any kind to this cladded vessel, then you might consider if you can safely overlook the NACE requirements for the base metal. I still have my reservations...did you check the entire surface of the CRA plate for manufacturing defects? Did you double check? If not, select the base material compliant with NACE requirements.
Cheers,
gr2vessels

RE: MR0175 & Cladding

The only thing that will be required for the carbon steel to notionally comply with ISO 15156-2 is a hardness of 22HRC.  Was that achieved (by good fortune) in the parent steel and welds, including the HAZ from the weld overlay?  If it was not, you are then into a risk and reliability assessment:  reliability of the overlay NDT, reliability of the overlay in service and risk of failure of the carbon steel.  Also, please note the use of the words 'long term'.  'Proper QA/QC' isn't 10 years in service!

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

RE: MR0175 & Cladding

(OP)
sjones:

In this case, we are not considering weld overlay. Either explosion or roll bond cladding.

RE: MR0175 & Cladding

OK but you will still have to back weld any weld seams in the item under construction.

It's all a matter of risk.  What does it cost to get the carbon steel with ISO 15156 requirements versus what will it cost (in people, assets, environment, reputation terms) if there is a loss of containment?  Otherwise known as ALARP.

 

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources