Addional RT per B31.4
Addional RT per B31.4
(OP)
Is there any statement in B31.4 that cite the two additional joint shall be inspected when the result of a joint girth weld reveal "rejected"?
This is a flowline with hydrocarbon services. RT was performed by 10% randomly.
This is a flowline with hydrocarbon services. RT was performed by 10% randomly.





RE: Addional RT per B31.4
The APIGUY....