INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

NDE of Dish Head Seam Welds

NDE of Dish Head Seam Welds

NDE of Dish Head Seam Welds

(OP)
Hello Members

The specification for manufacture of coded pressure vessels
stipulates that if the dish head (SA 516 Gr 70 2:1 semi ellipsoidal)is made of more than one plate, the seam joint shall be 100% radiographed prior to forming.In a previous project the requirement of 100% NDE requirement was after forming.Is there any reference in ASME sec VIII as to when NDE is to be carried out?

On analysing both options I can conclude,

1) If RT is specified to be done before forming we are ensuring that the weld is accepted before forming and we are minimising repairs  after cold working on the dish heads. If some visible defects develop during forming they only need to be repaired and there is less potential for hot works on formed surface.

Demerits:
1)We may not capture the defects which have developed internally due to forming

2 If RT is specified after forming ,the defects if any which have developed internally due to forming are also captured during RT along with the original seam welds

Demerits: there is potential for more hot works during repairs on cold formed dish head surface

Would like to have some inputs

Thanks in advance

Sree


 

RE: NDE of Dish Head Seam Welds

The RT should be done after forming. You can always perform addition RT before forming, this is up to you.

Codes and Standards do not provide detailed process steps both for forming or NDT sequence of events. Only that NDT, if specified, is normally after fabrication process steps are completed.

RE: NDE of Dish Head Seam Welds

(OP)
Thanks metengr
I think we can consider this forming similar to heat treatment operation. Most codes and specifications stipulate NDE after heat treatment whereas  fabricators carry out internal NDE before heat treatment to be on the safer side.

sree
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources