INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Hydrotest of Pressure vessels

Hydrotest of Pressure vessels

Hydrotest of Pressure vessels

(OP)
The client specification for hydrotest of pressure vessels states that"All hydrostatic tests shall be done in presence of AI/companys's authorised representative.
Vessels shall not be previously tested by the vendor.

In what way is the last line above(Vessels shall not be previously tested by the vendor.)  to be interpreted?

a)AI/Company rep   shall witness the hydrotest of vessels
The vessels shall not be tested in their absence

b) vessels shall not be tested before final hydrotest which prohibits contractor to carry out even internal hydrotest. Only one time the testing is permitted .

I tend to agree with a) .

i would like some inputs on the interpretation.

Thanks in anticipation
sree60

 

RE: Hydrotest of Pressure vessels

I can only guess....as others may as well.....the only way you will get the right answer is by asking the client who wrote the specification.....I would guess that they want the first test to be witnessed by both the AI and the Company representative and yes, this would imply no internal testing allowed prior to AI/Company Rep Witnessing....the way I look at it, this way they will be able to know how good your shop really is at fabrication ....My $0.02

FAQ731-376: Eng-Tips.com Forum Policies

RE: Hydrotest of Pressure vessels

The vessel will be pumped up and made ready for AI/client inspector.  They don't have to be there for make ready and pumping.  Make sure you have a chart recorder on it as a record.

No previous hydrotest is to make sure client inspector is there to see if there is any ""repairs"" frantically being made to hold water.

Good practice

RE: Hydrotest of Pressure vessels

Agree with the above responses.

RE: Hydrotest of Pressure vessels

I guess your client is putting QA/QC concepts into the spec. Typically if a boiler or pressure vessel can pass the first and single hydro test it can be considered of very good build and/or installation quality. If something failed an earlier inspection, typical QA/QC would become more suspicious and require more stringent tests. This not normally an AI's job but prior failures does raise his/her concern on quality and manufactures might not want to show these earlier records.
 

RE: Hydrotest of Pressure vessels

(OP)
Thanks to everyone for the valuable inputs.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources