INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Foundation Pour Lengths

Foundation Pour Lengths

Foundation Pour Lengths

(OP)
I've read previous posts about limitations on concrete pour lengths in concrete tanks, but I haven't found anything regarding standard foundations.  I have a project under construction using concrete trench footings and standard wall footings.  We require construction joints at a maximum spacing of 60'. This has been part of our standard structural notes and we've never had a problem with it before but the contractor says that this limitation throws off their schedule (even though it should've been in his bid) and asked if we could lose this limitation.  We told them that we couldn't and that they should leave between 5' and 60' between adjacent pours and wait 7 days between the infill pour and to limit the shrinkage effects.

I just wanted to know if we're being too strict on these limitations and what, if any, others use for the limitations on pour lengths.
 

RE: Foundation Pour Lengths

If these are buried foundation walls, or retaining walls with earth full height or close on one side, I would agree with the contrator.  

However, with no earth present to serve as a heat sink and thermal barrier, I would stick to your guns here.

Mike McCann
MMC Engineering

RE: Foundation Pour Lengths

If the retaining wall (yielding) is exposed to weather on one side and not part of a heated building structure, it will need expansion/contraction joints too.

Mike McCann
MMC Engineering

RE: Foundation Pour Lengths

(OP)
The project is multiple buildings, so some are earth formed trench footings, and others are formed footings with stem walls.  All will be buried foundations so they're not retaining soil and aren't under any flexural stresses.  Which part do you feel is too strict?  The length or the delay in adjacent pours?  We are thinking that we will stick to the 60' length, but allow them to pour adjacent pours the following day as opposed to waiting 7 days.

RE: Foundation Pour Lengths

If there are specific places you want to read the shrinkaqe cracks, then stick to your 60 foot limit, where is where they will show.  

However, as a buried trench footing and/or stem wall, and if they are not visible, what's the harm in a monopour of the entire strip footing regardless of length?  Variations in temperature will not be an issue here, only shrinkage, which can be limited by the amount of water in the mix.

That will be the problem though - the water added to the mix on-site by the cobntractor and truck operator to get it out of the truck quickly.  That will add to the shrinkage.

Mike McCann
MMC Engineering

RE: Foundation Pour Lengths

(OP)
Thanks, I appreciate the help.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources