INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Asphalt Paving
3

Asphalt Paving

Asphalt Paving

(OP)
We finished laying asphalt (BM 25.0) on Saturday. During the operation everything was done and tested according to VDOT (Roller pattern, control strip, etc). We took core samples the same day and they were test by noon of the following day. I just got the results of the density test performed on the samples and non of the samples met the required 95% density. What options do we have to correct this problem?

RE: Asphalt Paving

If it is a state project, the usual procedure is to reduce the pay to the contractor based on a sliding scale of density.

If the density is significantly off, you might require the contractor to mill and overlay.

How low was the density?  Was the density in the field compared to lab density or a control strip density?  What size cores were used?  Do you know if the testing was performed properly?

What do you think caused the low density?  Was it placed too cold?  Was the equipment too light or did break-down rolling not occur quickly enough?  Was the mix design "off".  Is this a "SuperPave" mix?

RE: Asphalt Paving

Ron is right, there is a reason for the low densities and it will help to know why. Any weather problems? or the layer thickness low? If no obvious reason I would wonder about the testing and consider testing again.

RE: Asphalt Paving

Coring pavements the same day they are paved typically requires special cooling measures at the core location such as ice to firm up the pavement enough to not cause damage during coring or core removal.  Without cooling there is a high potential for deformation of the core, leading to lower density determinations.  Waiting until the next day to measure them can also lead to deformation if the cores are not stored properly or are not kept cool enough.

Greg

RE: Asphalt Paving

Coring pavements the same day they are paved typically requires special cooling measures at the core location such as ice to firm up the pavement enough to not cause damage during coring or core removal.  Without cooling there is a high potential for deformation of the core, leading to lower density determinations.  Waiting until the next day to measure them can also lead to additional deformation if the cores are not stored properly or are not kept cool enough.

Greg

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources