INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Claim for Unusually Severe Rainfall

Claim for Unusually Severe Rainfall

Claim for Unusually Severe Rainfall

(OP)
Here is the set up:

1.  Project is 6 months duration USACE contract to excavate a borrow pit and build an earthen levee.

2.  There are 4 pay items
 (a.) embankment placement (borow pit is inclusive)
 (b.) outlet ditch 1 in borrow pit
 (c.) outlet ditch 2 in borrow pit
 (d.) seeding and fertilizing

3.  Adverse weather calander in contract reflects the following adverse weather days:
  (a.) march 5 april 5 may 4 june 4 july 5 aug 5

4.  Contract does not state any precipitation levels but does refer the contractor to NOAA or NWS for historical levels for the construction period.

5.  Each month has experieced triple the weather days and double the monthly inches of rainfall (20year avg).


With that out of the way here is the problem in a nutshell:

Project is in the 7th month- no LDs due to the additional days added for the unusally severe rainfall and subsequent wet conditions.  No disagreement on the number of "no work" days.  However, due to the abnormal rainfall and the quantity of "no work" days we have lost money due to increased equipment cost, increased soil processing due to significantly higher moisture content from the rain, and increased field overhead cost from the increased number of days on the job.

Question:  In past projects I was always happy to get the days because impact was not on this level, however, im interested in pursuing an REA under "Differing Site Conditions" or "Changed Site Conditions".

Is this possibler?

Thanks,       

RE: Claim for Unusually Severe Rainfall

Yes.  If you can show through NWS data that the number of allowance days set out in the contract were insufficient, you have a good shot at a claim.  I would suggest that you engage a construction attorney who has claims experience to help you through the process.  You will also need an expert in construction delays/delay claims to support your contention.

Try direct negotiation with the contract manager first, then go the legal route if that doesn't work.  Do your homework and make sure your case is locked tight.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources