INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Precast Box Culvert in Influence of Footing

Precast Box Culvert in Influence of Footing

Precast Box Culvert in Influence of Footing

(OP)
I have designed a building with shallow footings. It is in the middle of the campus and the owner has hired another firm to design an underground utility box culvert tunnel. For the most part this is not an issue. However, at one location, the tunnel gets to be within 6 feet of the outside face of the building I am designing. The top of the box culvert is 18 feet below the bottom of my footing. The box culvert will be installed first. I would like to have the box culvert designed to carry the load due to the influence of the footing.

The contractor has suggested dropping the shallow footing down so that neither the footing or the tunnel creates surcharge on the other. In my opinion, it becomes unreasonable to have a shallow footing go from 4' below grade to 27' below grade. To me, this is no longer a "shallow" footing. I am having trouble justifying deep foundations for the four footings that lie close to where the box culvert tunnel will be placed. I am especially troubled by mixing systems and getting differential settlement.

I understand the argument that I need to consider if the building would remain stable is the box culvert needed to be removed/repaired in the future, but at the same time, these are lightly loaded footings (less than 40k each) and I'd argue if there are future issues, appropriate shoring could be designed.

Any recommendations on the best way to proceed here?

RE: Precast Box Culvert in Influence of Footing

Have the box culvert designed for the appropriate surcharge and have a geotech inspector sign off on the backfill and compaction.

 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources