INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

High Voltage Generator Testing

High Voltage Generator Testing

High Voltage Generator Testing

(OP)
Hey guys, I am working at a project now where there is a KATO 13.8KV (4.4 MW, parralled to the local utility grid) generator being used to supply power to a building in Manhattan. The generator is powered by a Solar Gas Turbine (a Mercury 50).

Can someone give me a brief rundown of the high voltage generator and switchgear tests that should be performed, and also explain why you would perform it and how the test works. Its not my responsibility to do this stuff, but I would like to be able to understand what is going on.

Thanks in advance for any help.

RE: High Voltage Generator Testing

Find a copy of the NETA acceptance test book, free or low cost cost from the web.

RE: High Voltage Generator Testing

You might find Doble's website quite educational: www.doble.com
  

----------------------------------
  
If we learn from our mistakes I'm getting a great education!
 

RE: High Voltage Generator Testing

Well, there are equipment tests and there are system integration tests.

Individual equipment tests are well described in NETA-Acceptance Testing Specifications.  The system tests depend on the system design objectives. That would include testing all possible reallife scenarios with and without loads.  The real test is go through all probable failure scenarios, that the system is expected to react to such as power outage, certain breaker failure, etc. to make sure that the system will function in emergency as expected.

Plus there are normal field acceptance tests that verifies all the adjustable settings and see that the system works as intended.

If the system designers are good enough, they should be able to explain this to your satisfaction. If not you need to hire some experienced professionals to watch your interest.

If you are wondering, if all these tests are needed, the answer is Yes or you will not know what you paid for. Also the star-up checks performed by field service techs are not sufficient for a through system acceptance tests.



 

Rafiq Bulsara
http://www.srengineersct.com

RE: High Voltage Generator Testing

By the way this includes electrical as well as mechanical tests, especially to check reliability of the fuel system, louver operations, etc.

Rafiq Bulsara
http://www.srengineersct.com

RE: High Voltage Generator Testing

NETA is a good reference.

By the other side, NEMA MG-1 also can be a good support for generator testing.

Regards

RE: High Voltage Generator Testing

(OP)
Thanks to everyone for the replies, they have been very helpful.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources