INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Auger Cast Grout Piles

Auger Cast Grout Piles

Auger Cast Grout Piles

(OP)
How many piles should be set aside at the begining, to be used for load tests before the execution phase of the construction of the Deep Foundations?

RE: Auger Cast Grout Piles

5% for all under 45 cm diameter
10% for all between 45 aln 100 cm
25% for all over 100 cm

must be tested in one or other way for "in situ" piles according to CTE.

However need not be load tests, (but integrity, sonic etc) for which a percentage is not set. For big numbers of piles in an "uniform" soil 1 to 3% should be more than enough.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources