Staged Construction of Embankment
Staged Construction of Embankment
(OP)
Hi guys, recently having a problem with staged constructions of high fill embankment. The embankment constructions were done in 2 stages to allow alternating traffic (i.e. stage 1 embankment constructed on one half of the road and then stage 2 on the other half of the road, following the completion of the stage 1).
However, cracking problems (or differential settlement) occurred between the interface of stage 1 and stage 2 embankments, which resulted in a weak zone in between. And I think this is mainly due to the different compaction levels applied for stage 1 and 2 (maybe the contractor did not compact the fill materials property in stage 1). Anyway, they are fixing the problem by applying reinforced fill and geogrid.
My question is: is this problem only related to improper compaction during the construction or there could've been some construction techniques need to be applied to make sure the appropriate joining of embankments done in different stages?
I hope ppl can understand what I'm trying to say. Cheers.
However, cracking problems (or differential settlement) occurred between the interface of stage 1 and stage 2 embankments, which resulted in a weak zone in between. And I think this is mainly due to the different compaction levels applied for stage 1 and 2 (maybe the contractor did not compact the fill materials property in stage 1). Anyway, they are fixing the problem by applying reinforced fill and geogrid.
My question is: is this problem only related to improper compaction during the construction or there could've been some construction techniques need to be applied to make sure the appropriate joining of embankments done in different stages?
I hope ppl can understand what I'm trying to say. Cheers.





RE: Staged Construction of Embankment
Has there been any actual settlement and is there faulting at the interface between the two?
Stage 1 would likely have insufficient compaction at the interface, while Stage 2 could be fully compacted against stage 1.
RE: Staged Construction of Embankment
But it gotta be some construction method to overcome this??
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
What is the embankment constructed with?
soil types? How consistent is the fill?
What is the subgrade composed of?
soil types? Soil Density?
How consistent are the soils?
Is there ground water at or near the original subgrade elevation?
What is the general climate for this project?
What weather conditions during construction?
RE: Staged Construction of Embankment
To your questions:
embankment is constructed with common fill (mostly cohesionless materials + some cohesive) with soaked CBR specified as > 3.
original subgrade is 1m basaltic clay underlain by basalt. The clay has a moderate swell of 2.5%.
GW is well below the original surface, say 5m below and has little impact on the project.
The area is relatively dry and not so sure about the construction time. It did not appear to be much related to drainage.
The thing I really want to know is, what is the 'correct' construction method/procedure for this type of works where you have to construction embankment in two stages?
RE: Staged Construction of Embankment
You've added 6M of fill over clay. While this would likely produce some settlement, it shouldn't be cause for differential lane settlement unless the clay layer is significantly different in character or thickness from one side to the other (again, not likely, but don't completely rule it out yet).
Has there been any lateral movement of the fill?
RE: Staged Construction of Embankment
We didn't notice any lateral movement, maybe it's too little to observe.
RE: Staged Construction of Embankment
If the interface layer(s) were not benched or notched-in as fill for phase 2 was brought up... it is almost certain to be a problem.
**With phase construction, this area (the joint) is usually an area well suited for temp. MSE wall or temp. spl. shoring if your fill slope has lateral width restriction(s), even with the shoring/temp.MSE "minimal" cracking can happen under certain conditions.**
If corrective action(s) are employed, cutting down and placing back will be expensive (if you have enough room to do it with traffic)
Do you have a typical or cross-section available? That would be nice.
RE: Staged Construction of Embankment
I agree on compaction problems at the interface (already explained).
From the project description, I'd also agree the foundation soil and the ground water is not an issue.
I'd think if the problem is strain as I described above, geogrid several feet below the finish grade would help, but that would also interfere with your staging.
Make sure you don't have a slope stability problem, wouldn't want to overlook something else. . .
f-d
¡papá gordo ain't no madre flaca!
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
I've got a little bit more information on the project. I've been given a photo of the site(see attached).
The stage 1 embankment has a temporary wire mesh/geotextile faced temporary retaining wall due to the limited space. And during the compaction at near the temp. retaining wall, the geotextile and the mesh tend to "bulge out", and I think this is the main reason for the insufficient compaction.
Is there a construction method which will enable the compaction to be achieved?
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
RE: Staged Construction of Embankment
Your sketch and pic were helpful in getting a better idea about your problem(s).
I cannot be sure this temp wall is the aggregate filled type that we use, and have not encountered temp walls that do not include an aggregate section...that is "not" to say that there are not one million and one out there, just none that I am familiar with.
The temp MSE wall standards we use require a system complete with calc.s and a seal, and are designed with-in very tight guidelines specifying minimum wire size spacing, aggregate size type, spacing and length of straps that project into the fill area. As with any system there are specific criteria including materials used and installation procedures that must be adhered to.
"When constructing wire faced walls it is critical that the area behind the face mat be completely filled with material and properly compacted....failure to do so will result in bulging of the face mats and settlement of the top of wall"...
As far as how to remediate this problem...you might get some input from the supplier of the wall system. I would guess they have encountered some of this in the past.
Good Luck
RE: Staged Construction of Embankment
Cheers,
RE: Staged Construction of Embankment
Our stnd. drawings and spec.s are proprietary. I would suggest you contact a US DOT (state or Fed. level) and review there standards and spec.s
The walls I have referred to have been around for quite some time.
Have you contacted the manufacturer and or designer of the system you have installed?
I would be interested in what they have to say in the matter.