Load test
Load test
(OP)
For an Emergency DG set of 1600 KW , the spec requires Full load run test to be done for 8 hours. But the vendors are offering to have only for 1 hr to 2 hour only. Whether full load test runs duration are based on the capacity of the Generator or for all the Generators?
Similarly whether it is a must to have a100% CO2 back up set of bottles as per NFPA 12 for a safe area installation?
Thanks to clarify
Similarly whether it is a must to have a100% CO2 back up set of bottles as per NFPA 12 for a safe area installation?
Thanks to clarify






RE: Load test
Bill
--------------------
"Why not the best?"
Jimmy Carter
RE: Load test
old field guy