Recently I was approched by a superior and asked if I would be willing to pursue aquiring a stamp for new construction of power boilers for our company.
I have always been on the construction side and not the buisiness liscening side and before I commit I would like information or advice.
Can some one offer information (USA)?
I have always been on the construction side and not the buisiness liscening side and before I commit I would like information or advice.
Can some one offer information (USA)?





RE: liscence and stamp requirments
The stamps relevant to you are:
* V Code Symbol Stamp
* A code Symbol Stamp
* M Code Symbol Stamp
* PP code Symbol Stamp
* S code symbol Stamp
* E code symbol stamp
Cheers,
gr2vessels
RE: liscence and stamp requirments