INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME Vessel in Western Australia
2

ASME Vessel in Western Australia

ASME Vessel in Western Australia

(OP)
We are planning to build vessel outside Australia & import it in Western Australia. Following are some of the doubts we have-

What are the requirements for import of an ASME U stamped pressure vessel to Western Australia?

If we already have ASME U stamp, do we still need to get the vessels design reviewed and certified by an Australian third party for compliance with AS 1210?

Do we need to  re-hydrotested the vessel  in the presence of a local accredited inspector (for certification)?

Your response with reference will be greatly appreciated.

RE: ASME Vessel in Western Australia

2
Drummaker,
First of all, you should contact Worksafe in Perth to obtain the specific requirements for design and plant registration. They will provide also the list of approved design verifiers and the specific requirements the plant will have to comply with. This forum cannot provide you those specific requirements.
Yes, you will need to prove the compliance with AS 1210 some specific requirements, the like you mentioned hydrotest, in the presence of a local accredited inspector. Before the re-hydrotest, make sure the design calculations will prove that the vessel will not be over-stressed, otherwise will not be permitted to operate in Australia.  However, please note that in most of the cases where the ASME VIII design is complete and include detailed MAWP calculations, the hydrotest pressure is at or even higher than that required in AS 1210. Also, you can impose a higher hydrotest pressure in the original design if required for compliance with AS 1210. Be aware however, that compliance might also require the use reduced allowable stresses as per AS 1210, not as per ASME II Table D.
By the way, the U stamp doesn't have much meaning to the local authorities, except perhaps for the insurer.
Cheers,
gr2vessels

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.