INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Hydrotest
2

Hydrotest

Hydrotest

(OP)
Dear All,

I'm following the supply for Equipment which is designed in accordance with ASME VIII Div.1 but the design pressure is equal to atmospheric pressure.
As scheduled on relevant QCP the Vessel shall be subjected to Hydrotest full water filling it in Vertical position.
Some days before the mentioned test the Vendor has asked me to perform a 100% LP on main welds only for the following reasons:
- The Hydrotest in Vertical position cannot be carried out considering that the Vessel weight full water filled is too high.
- The Hydrotest in Horizontal position cannot be carried out considering that on the center top head of Vessel there is an inspection opening (see attached file - two halves - DN1000) no leak proof.

Any suggestions on the matter would be greatly appreciated.
Thanks in advance.
 

RE: Hydrotest

did your QCP call out any NDE on the root welds?

Steven C
Senior Member
ThirdPartyInspections.com

RE: Hydrotest

(OP)
QCP calls out a Visual Weld Examination and a Radiograpic examination only.

RE: Hydrotest

when were xrays performed root or finished weld?

Steven C
Senior Member
ThirdPartyInspections.com

RE: Hydrotest

You could weld on a temporary cover for the hydrotest.

RE: Hydrotest

(OP)
Thanks for both your helps.

Anyway the Vessel is designed with Xray Spot (joint efficiency=0.85) so that the X-Ray are performed spot on main welds (longitudinal and circunferential) includung cross-welds.
The top dished head in fully radiographed and LP tsted.

EyeC
Maybe I think that the X-rays were performed on finished welds.
I'll make you confirmation asap.
Thank you again.

 

RE: Hydrotest

what percent of welds were xrayed

Steven C
Senior Member
ThirdPartyInspections.com

RE: Hydrotest

Well...assuming it is designed and built per code and not stamped.

those covers on top head will not hold much/in any pressure.

The only way to test this, if structure and vessel will withstand the weight, is to fill it up after it is erected.

Another way is to weld on test covers at those openings on heads and do a pnuematic test with pressure at vertical height of vessel times 0.433 and hope all your welds are good.

Your client may accept full mt/pt or ut in lieu of testing.

RE: Hydrotest

were there any reject/re-weld for those welds xrayed?

if no, then i would not be concerned with the welds or lp of them.

is this a hopper for a feeder for light weight materials - looks familiar?

i think the concern of the vendor is valid and would look at   welding a blind on the inspection opening and do a pneumatic test @ LOW PRESSURE

Steven C
Senior Member
ThirdPartyInspections.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources