i am involved in a job in installing new MSV skid (2 already existing) where 16" bulk header is extended for a length of 15m. Will the pipe needs to be stress analysed? Design temp. 82 deg C. Rating 600#
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
|
RE: Stress analysis
jt
RE: Stress analysis
RE: Stress analysis
**********************
"Pumping accounts for 20% of the world's energy used by electric motors and 25-50% of the total electrical energy usage in certain industrial facilities."-DOE statistic (Note: Make that 99% for pipeline companies) http://virtualpipeline.spaces.live.com/
RE: Stress analysis
It is not correct to say a priori that this line, or any line for that matter, does not need a stress analysis.
Not sure what Code your system is under, but you better check that out first. Pete