INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

raft/mat for telecom tower

raft/mat for telecom tower

raft/mat for telecom tower

(OP)
Wind load on tower cause uplift, down thrust and horizontal shear on base of tower.some legs experience uplift with horizontal shear(one way or both way) and some large down thrust along with horizontal shears at base.While designing foundation, if isolated footing is not adequate and, therefore, mat/ raft is to be considered, how to treat the problem since there be large eccentricity due to overturning action? can any one suggest me the appropriate method of raft/mat designing in this case?

RE: raft/mat for telecom tower

Have you considered three caissons?  How about driven piling in three locations.

For your mat alternative I suspect that bearing capacity at the toe is not most critical, but that with a mat you might need great footing thickness for uplift resistance.   Would you then rotate about the toe?  I think not. I'd not consider a pressure distribution with any zero presume areas.

For triangular pressure distribution, a common assumption is to use the recommended "bearing capacity" as that toe pressure to minimize toe settlement.  Other discussors might not agree.

RE: raft/mat for telecom tower

Pile/cassion foundation should be considered as suggested above.

But, as a practice, I will start to estimate the size of the mat foundation:

1. Obtain max e caused by loads on towewr.
2. estimate depth using punching shear relationship (assume bo=4d, h=d+4" or 6").
3. estimate min width by solving (for square footing)
   (P/B^2)*(1+6e/B)+unit pressure of concrete <= fa, and
   (P/B^2)*(1-6e/B)+unit pressure of concrete >=0.
    Choose whichever is larger.

Then check overturning and sliding stability, increase thickness as necessary.

RE: raft/mat for telecom tower

Agree with above, but I would start with checking for overturning and then up the size as required to satisfy bearing pressure limitations.

slab effectively acts as an upside down cantilever under the action of the bearing pressure (dont forget to factor it up).

Also Helical piles are good for these things as their uplift is basically the same as their downward capacity.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources