INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Monolithic Isolation Joint

Monolithic Isolation Joint

Monolithic Isolation Joint

(OP)

 I have a monolithic isolation joint that has to welded into a ethane/propane line.Engineering requirements are B31.3.The pipe  is 12 inch, sch. 120, P1 material which requires PWHT.The problem is the isolating filling material and ring are located approx. 12 in. from the weld which is only designed for 175F. Is it acceptable to weld this joint with inco 82 without PWHT and meet B31.3?  

RE: Monolithic Isolation Joint

As per 331.2.3 b), not directly but you could try invoking 331.2.2 and doing some fitness for service work on the WPS/PQR.

Steve Jones
Materials & Corrosion Engineer
http://www.linkedin.com/pub/8/83b/b04
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources