INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Alternative work schedule (9/80)

Alternative work schedule (9/80)

Alternative work schedule (9/80)

(OP)
I would like to get some input on how to ideally handle alternative work schedules.  My company works on a 9/80 schedule; 9 hours Monday through Thursday, 8 hours one Friday, and the alternate Friday off. I created a standard calendar with the non-working Fridays identified every fortnight, and adjusted the working time for Monday - Thursday to be 9 hours. I have the calendar displayed to be this calendar. The resources for the company are all referencing this calendar.

When I create tasks, however, the hours are not coming out right. For example, a three day task that starts on Monday will still only register for 24 hours not 27!

I would appreciate any assistance, as I am trying to use Project to estimate resources to manage my time and to produce reliable quotes.

Best regards,

Matthew Ian Loew
m.loew@ssss.com

RE: Alternative work schedule (9/80)

You have setup the calendar correctly for your resources, and have each resources using that given calendar.

Check the following two spots which will be utilized to calculate the time duration for task.

On the your gantt chart highlight the desired task.
Double click in the grey area and a Task Information sheet should appear.
Go to the advance tab.
Under calendar select your calendar which shows your companies working time.
Check that the times are as per your estimates.

The second spot to check is the Task Type.
If the task is to be fixed amount of time, no matter how many resources are added, the select "Fixed Duration". If you have a set amount of time, but you do not care the percentage of each resource is assigned to your task select "Fixed Work" it automatically calculates the resource percentage (this may mess up your resource calculation though).  The default is "Fixed Units" and the time is automatically calculated (reduced) as you add or subtract resources.

Hope this helps.

Babyyoda

RE: Alternative work schedule (9/80)

(OP)
babyyoda,

Thanks for the help. Still will only show 24 hours (3x8) when 3 days are entered as the duration. I am looking for 27 hours with 3 nine hour days. I can hard code the full number of hours, but even that will mess around with the % of the resources. Very frustrating.


Best regards,

Matthew Ian Loew

RE: Alternative work schedule (9/80)

Hi Matthew,

I gave it a try.  Any you are right, if you enter the duration as 3 days it calculates 24 hours.  However, if you enter the duration in hours (27 h), it shows the proper time frame.  If I find a better way I will let you know.  

Babyyoda

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources