P6: Updating Progress - Period Financials
P6: Updating Progress - Period Financials
(OP)
Currently, all activities within the schedule have been resource loaded (include. costs).
ADMIN>Financial Periods:
I would like to create the following Financial Periods.
27-Dec-08 to 30-Jan-09
31-Jan-09 to 27-Feb09
28-Feb-09 to 27-Mar-09
..... to 30-Sep-09
Note: Period ends on the Last Friday of every month and begins on the following day.
I created these manually and it appears to be in order. However, I changed the Batch Start and End dates to be 27-Dec-08 to 30-Sep-09, respectively. After selecting "Batch Create" the dates change.
Can anyone offer a step by step so that I can confirm that these periods have been created correctly?
Thanks in advance
ADMIN>Financial Periods:
I would like to create the following Financial Periods.
27-Dec-08 to 30-Jan-09
31-Jan-09 to 27-Feb09
28-Feb-09 to 27-Mar-09
..... to 30-Sep-09
Note: Period ends on the Last Friday of every month and begins on the following day.
I created these manually and it appears to be in order. However, I changed the Batch Start and End dates to be 27-Dec-08 to 30-Sep-09, respectively. After selecting "Batch Create" the dates change.
Can anyone offer a step by step so that I can confirm that these periods have been created correctly?
Thanks in advance