INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Setting a GE T35

Setting a GE T35

Setting a GE T35

(OP)
Hello,
I am working with a GE T35 relay, and I'm stuck on how to determine the appropriate setting for Slope 1.  I have a GE document for T60 percent calculations, and it summarizes the Slope calculations as

[(delta Id)/(delta Ir)]*100%

where Id is the differential current and Ir is the restraint current.  Defined as:

Id = i1_comp + i2_comp (shown as vectors)
Ir = max(|i1_comp|,|i2_comp|)

"comp" is never defined, although I assume it means magnitude compensated.

The definition of Slope 1 is the slope setting from pick-up to break 1, and it is based on CT errors during normal load currents and from tap changes.

Okay, so what I want is a clearly written equation for how I set slope 1.  Does anyone have such an equation?

thanks

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources