PSS/E Dynamic simulation
PSS/E Dynamic simulation
(OP)
Hi
Can anyone tell me step by step guide to dynamic simulation with PSS/E activities for the following case,
1 Tripping of a generator
2 Three phase earth fault at a bus (say 220 kv) what are the critical clearing times that are widely used.
Can anyone tell me step by step guide to dynamic simulation with PSS/E activities for the following case,
1 Tripping of a generator
2 Three phase earth fault at a bus (say 220 kv) what are the critical clearing times that are widely used.






RE: PSS/E Dynamic simulation
No one is here to work for you.
RE: PSS/E Dynamic simulation
Shall I put my question this way,
1 I prepaired the case for stability run
( I have 7 generators in my case)
2 saved the case for pssds4
3 From pssds4 entry point I did following;
4 perform base stability run
I choose rotor angle of generators for the channel 1 to 6
(My case has 7 generators I'm going to trip one)
5 run the case. Then upto what time I have to run( value for Tpause) to trip a generator ? 0 or 1 second